Project

96 Meter Lürssen

The job

OEM Yacht Service upgraded the software and hardware of the yacht’s equipment control systems, including a complete new control system for the MOB foredeck crane.

Control Technology

OEM installed its latest PLC software on the aft and midship equipment control systems. For the Nautical Structures MOB crane, OEM built, installed, programmed and commissioned a new control cabinet.

Delivered

  • •New OEM PLC software, aft and midship equipment control systems
  • •PLC upgrade MOB foredeck crane (Nautical Structures)
  • •Production and installation of new control cabinet
  • •PLC programming and commissioning
  • •Programming support for new proportional hydraulic cards (bow thruster)

Fact sheet

TypeUpgrade
Vessel96 m motor yacht
LocationPalma de Mallorca – St. Maarten
Duration
DisciplinesElectrical control systems, Tender Cranes, Hydraulic systems